AGENDA REQUEST
GENERAL DISCUSSION ITEM
Subject:
title
15 Stoddards Wharf Road Sewer Request continued.
end
Background:
From October 28, 2025:
Ms. Wadecki said more details need to be put into the second paragraph; it implies that it is for
sewer "installed facilities" but needs a more specific explanation. The water and sewer lines
plans are referenced but should also be included. Other sections need amending to fix
inconsistencies, and redundancies. Chairman Lynch said "in the vicinity of Colby Drive" should
be changed to refer to the Bill Library not Colby Drive. It was also agreed that "Stoddards
Wharf" is confusing. Removal of paragraph one and the referral of that paragraph from 3a was
Suggested.
ACTION ITEM:
Revise the Water and Sewer Main Extension Agreement for the November agenda.
From September 23, 2025:
Chairman Lynch said that the developer would like to put in 103 units and added that the WPCA
has approval from Weston & Sampson that would allow usage of 90 gallons per day per unit.
The 12 commercial units are a possible concern. The average estimated usage is 1,000 gallons a
day but that depends on what kind of commercial business goes into the unit. Chairman Lynch
said for example if a Starbucks is put in a commercial unit the average usage would be
approximately 5,000 gallons a day. Chairman Lynch said there would need to be a caveat in the
agreement that if more than 1,000 gallons a day is used by the commercial units the agreement
will need to be re-negotiated.
ACTION ITEM:
Chairman Lynch will draft a Stoddards Wharf sewer installation commitment letter including a
caveat for the Authority to review in the event more sewer needs to be processed.