MOTION to approve STV Construction, Inc., change order requests for Owner’s Representative Agreement for Ledyard School Roof Projects in the following amounts:
BOE Central Office - $952.00
Gales Ferry School - $13,056.00
Juliet Long School - $2,176.00
In addition, approve Agreement Amendment between STV Construction, Inc., and The Town of Ledyard dated 1.29.2025 for a total Amended Contract Value of $110,616.00 for Owner’s Representative Agreement - Ledyard School Roof Projects.