City of Ledyard CT header
File #: 24-1059    Version: 1 Name:
Type: General Discussion Status: Agenda Ready
File created: 11/20/2024 In control: Water Pollution Control Authority
On agenda: 11/26/2024 Final action:
Title: Review of Trail/Sewer line continued - progress report.
Attachments: 1. image003, 2. Gerber April Invoice, 3. Gerber May Invoice, 4. Ledyard Sewer - Route 117 7-25-24, 5. Ledyard Sewer - Fairway 7-25-24, 6. Town Council mtg minutes 9-11-24, 7. Ledyard Low Pressure Sewer Upgrade Phase 3 BID
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA REQUEST

GENERAL DISCUSSION ITEM

 

Subject:

title

Review of Trail/Sewer line continued - progress report.

end

 

 

Background:

 

During the August 27, 2024, meeting the Authority discussed proceeding with the Weston and Sampson Engineering design of sewer mains along Route 117 Bid number 2021-03 Amendment 4, at a cost of $137,500 depending on availability of funding and Fairway/Colby Drive Bid Number 2021-03 Amendment 3, at a cost of $108,000 subject to availability of funds after funding Amendment 4.

 

The Authority made the following motions:

Motion to recommend APPROVAL of the preliminary Weston and Sampson Amendment 4 Route 117 design subject to availability of funding.

 

Motion to recommend APPROVAL of the preliminary Weston and Sampson Amendment 3 Fairway Drive design subject to availability of funding after funding Amendment 4.

 

During the Town Council meeting on September 11, 2024, the two recommendations were approved.

 

Department Comment/Recommendation:

(type text here)