City of Ledyard CT header
File #: 24-1140    Version: 1 Name:
Type: General Discussion Status: Filed
File created: 12/4/2024 In control: Water Pollution Control Authority
On agenda: 12/17/2024 Final action: 12/17/2024
Title: Lead Survey Review and Grant Submittal - update.
Attachments: 1. 2024-5-10 Ledyard WPCA-LSL Inventory & Replacement Plan Screening, 2. Document_2024-04-24_195948, 3. Ledyard Water System and Gales Ferry System_DWSRF Eligibility Application, 4. DPH_email, 5. CT0727051_GalesFerry_LCRR_Inventory_Initial_10-12-24, 6. CT0727091_Ledyard Center_LCRR_Inventory_Initial_10-12-24, 7. LSLI FAQ - Working Doc V.1 11-07-2024, 8. Lead_Survey_Questionaire, 9. CT0727091 LWPCA Ledyard Center PbCu, 10. CT0727091 13 Cartridge Trail Pb results pages Fall 2024, 11. CT0727091 Fall 2024 Pb_Cu results, 12. CT0727091 Summary page Pb 13 Cartridge Trail Fall 2024

AGENDA REQUEST

GENERAL DISCUSSION ITEM

 

Subject:

title

Lead Survey Review and Grant Submittal - update.

end

 

 

Background:

From the July 23, 2024, meeting:

Groton Utilities is still proceeding with the survey.

 

From the September 24, 2024, meeting:

Chairman Lynch said that the DPH approved the WPCA's application. There is a public hearing on September 25, 2024, at 10:00 a.m. which Chairman Lynch registered to attend. The grant would cover 25% to 50% of the cost. Chairman Lynch will also meet with GU regarding the grant. GU must submit the final plan to the DPH by the end of October.

 

From the October 22, 2024, meeting:

Chairman Lynch said the lead survey was signed by Mayor Fred Allyn III and submitted. He added that the WPCA is receiving a grant, but the amount is unknown. It can be anywhere from twenty-five to fifty percent. Chairman Lynch will be attending a meeting with Groton Utilities on November 15, 2024, GU is taking the leadership on the survey.

 