741 Colonel Ledyard Highway  
Ledyard, Connecticut 06339  
TOWN OF LEDYARD  
Permanent Municipal Building  
Committee  
Meeting Minutes - Draft Minutes  
Chairman  
Joseph Gush  
Special Meeting  
Monday, April 14, 2025  
WORKING DRAFT  
5:30 PM  
Town Hall Annex - Hybrid Format  
REMOTE MEETING INFORMATION  
Join Zoom Meeting  
Meeting ID: 847 1686 9351 Passcode: 839088 • +1 646 558 8656 US (New York)  
I.  
CALL TO ORDER  
Chairman Gush called the meeting to order at 5:30 p.m. at the Council Chambers, Town Hall  
Annex Building.  
II.  
ROLL CALL  
Committee Member Gary Schneider  
Committee Member Gerald Tyminski  
Chairperson Joseph Gush  
Present  
Committee Member George Hosey  
BOE Representative Jennifer Reguin  
BOE Representative Kate DiPalma-Herb  
Excused  
Absent  
Committee Member Elizabeth Peterson  
In addition, the following were present:  
Mathew Bonin - Finance Director  
April Brunelle - Town Council Liaison  
Kristen Chapman - Mayoral Assistant, PMBC Support Staff  
Wayne Donaldson - Director of Facilities BOE  
Vincent Salinas - STV  
III.  
IV.  
RESIDENTS & PROPERTY OWNERS COMMENTS (Comments Limited to Three (3)  
Minutes)  
None  
UPDATE ON JULIET LONG, GALES FERRY AND BOE CENTRAL OFFICE  
PROJECTS  
Progress Reports/Field Observations  
RECEIVED AND FILED  
1.  
2.  
RESULT:  
Update/Discussion on Roof Projects & Budget Documents  
Mr. Donaldson stated there has been no change on the Central Office since the last meeting. The  
next step is for Garland to create the punch list at which point the Contractor will certify the  
punch list is complete. The Architect will then perform a walkthrough and create the final punch  
list. There are some minor issues to complete around overflow drains.  
Mr. Donaldson shared that Juliet Long is progressing on the solar portion, but were unable to  
work most of last week due to testing in the school. There will be testing over the following two  
weeks and Mr. Donaldson will provide that schedule to the Contractor.  
Mr. Donaldson discussed the progress at Gales Ferry School. Mr. Donaldson stated the radial  
section has not been completed, The Contractor was to cut a sample panel to see how the seam  
lines line up, hopefully that will occur Thursday or Friday of this week. Mr. Donaldson is  
hoping for something to look at and to approve that section. Mr. Donaldson believes the only  
item left is the bus canopy which is partially completed. Mr. Donaldson shared some issues  
regarding how the canopy met the roof which has been resolved. Once that is complete the  
Manufacturer will prepare their punch list and then the Architect will complete the final punch  
list.  
Mr. Donaldson referred to the budget document stating the document attached is not completely  
accurate per project. There are a lot of items that have not been subtracted and or added, as the  
change orders have been penciled in. Allowances built into the Contract also have to be taken  
back out on change orders. Items such as bonding and interest need to be adjusted based upon  
the value of the projects. There will be some significant changes to the budget document. Mr.  
Hosey questioned the figures listed in the remaining invoice column. Mr. Salinas will double  
check those figures.  
DISCUSSED  
RESULT:  
MOTION to approve The Imperial Company Restoration Contractor, Inc. Payment Application  
dated 1.31.2024 in the amount of $78,075.42 for Project 24-135 Gales Ferry School.  
3.  
Mr. Donaldson stated they are comfortable releasing this invoice for payment based on many  
factors including the percentage of the roof complete, previously build and other items. Mr.  
Donldson stated they are comfortable there are enough remaining funds on the roof portion of  
this job and retainage to cover any possible claims or open items. Mr. Tymniski asked how late  
the Contractor is. Mr. Donaldson replied August 20th. Mr. Tyminski inquired what date was  
given to the Contractor that we would start to charge them. Mr. Dondlson confirmed it is the  
Contract completion date which is the 20th of August. The Committee discussed concerns  
regarding the payments as it pertains to the contractual completion date and additional costs  
associated with the project. Mr. Donaldson replied there is a meting with the Contractor and the  
Architect on Thursday to resolve the issue and anything further discussion should take place in  
Executive Session.  
APPROVED AND SO DECLARED  
George Hosey  
RESULT:  
MOVER:  
Gary Schneider  
SECONDER:  
AYE  
3
2
1
1
Schneider Gush Reguin  
Tyminski Hosey  
DiPalma-Herb  
Peterson  
NAY  
EXCUSED  
ABSENT  
MOTION to approve The Imperial Company Restoration Contractor, Inc. Payment Application  
dated 2.28.2025 in the amount of $40,850.00 for Project 24.135 Gales Ferry School.  
4.  
Mr. Donaldson stated the same issues in the previous motion apply.  
MOTION FAILED  
George Hosey  
RESULT:  
MOVER:  
Gary Schneider  
SECONDER:  
1
3
1
1
1
Schneider  
AYE  
Tyminski Hosey Reguin  
DiPalma-Herb  
Peterson  
NAY  
EXCUSED  
ABSENT  
ABSTAIN  
Gush  
MOTION to approve Gold Seal Roofing LLC Application and Certificate for Payment dated  
3.31.2025 in the amount of $165,540.00 for Juliet Long School - Roof Replacement and  
Photovoltaic Project.  
5.  
Mr. Donaldson stated this charge is for the portion of the solar and electric that has been  
completed to date.  
APPROVED AND SO DECLARED  
George Hosey  
RESULT:  
MOVER:  
Gary Schneider  
SECONDER:  
5
1
1
Schneider Tyminski Gush Hosey Reguin  
AYE  
DiPalma-Herb  
Peterson  
EXCUSED  
ABSENT  
V.  
1.  
STV AND SILVER PETRUCELLI & ASSOCIATES UPDATE OF ROOF AND SOLAR  
PROEJCTS  
MOTION to approve STV Inv# 90033917 dated 4.2.2025 in the amount of $13,750.54 for  
Ledyard Schools - Gales Ferry School.  
Mr. Donaldson confirmed this is the extension of the change order that was approved which was  
a flat fee.  
APPROVED AND SO DECLARED  
Gary Schneider  
RESULT:  
MOVER:  
Gerald Tyminski  
SECONDER:  
5
1
1
Schneider Tyminski Gush Hosey Reguin  
AYE  
DiPalma-Herb  
Peterson  
EXCUSED  
ABSENT  
MOTION to approve STV Inv# 90033916 dated 4.2.2025 in the amount of $6,380.80 for  
Ledyard Schools - Central Office.  
2.  
3.  
4.  
APPROVED AND SO DECLARED  
George Hosey  
RESULT:  
MOVER:  
Gary Schneider  
SECONDER:  
5
1
1
Schneider Tyminski Gush Hosey Reguin  
AYE  
DiPalma-Herb  
Peterson  
EXCUSED  
ABSENT  
MOTION to approve STV# 90033918 dated 4.2.2025 in the amount of $2,176.00 for Ledyard  
Schools - Juliet Long School.  
APPROVED AND SO DECLARED  
Gary Schneider  
RESULT:  
MOVER:  
George Hosey  
SECONDER:  
5
1
1
Schneider Tyminski Gush Hosey Reguin  
AYE  
DiPalma-Herb  
Peterson  
EXCUSED  
ABSENT  
Discussion and possible action on STV Change Order Requests.  
Mr. Donaldson stated this is a change order to carry STV through the balance of the project.  
These change orders are for time and material, if time is not used on the project there will be no  
bill. The figures on the change orders is the maximum amount  
to be invoiced.  
Motion to accept STV Change Order contract amendment by cover letter dated April 4, 2025 for  
Central Office not to exceed $14,134.00  
Discussion:  
Mr. Schneider questioned the charge for the Project Executive. The Committee questioned  
charges for Central Office, specifically regarding the Grant Administrator. Mr. Donaldson will  
request further clarification from STV.  
NO ACTION  
RESULT:  
Gerald Tyminski  
Gerald Tyminski  
MOVER:  
SECONDER:  
VI.  
1.  
JULIET LONG HVAC PROJECT UPDATES  
JWL HVAC Project 2024 Updates  
Mr. Donaldson has asked the Contractor to provide a breakdown of the work that can be  
completed within the original budget in order for the Contractor to have the project complete by  
November 2025. Mr. Donaldson added although the Town is trying to get this on a Referendum  
sometime in May,the request is to see what work we can do in the building within the original  
budget so the Contractor can start moving this summer, Mr. Donaldson added otherwise the  
project won't get done and the Contractor will not be able to work in the classrooms during the  
school year. Minimal work can be done in the classroom such as some finish work and hanging  
units, but blowing out walls and running duct work is not possible during the school year. The  
project would then get pushed off to next summer and there will be escalation costs. Chairman  
Gush stated his understanding they cannot do anything until it gets through Finance Committee  
and the Town Council. Mr. Donaldson stated he is asking the Contractor to do this and see what  
may be possible. Mr. Donaldson stated he would like to get that information for the Committee  
to make a decision on. Chairman Gush provided an overview of the project timeline to date.  
Chairman Gush stated he will be at the Town Council meeting on Wednesday to answer  
questions from the Council regarding the project. Chairman Gush also referenced his letter to  
the Town Council dated April 7, 2025 outlining the need for an increased appropriation. The  
Committee discussed the timeline the request would follow from Finance Committee to Town  
Council and then Referendum if approved. Mr. Tyminski stated that this will not get done this  
summer. Mr. Donaldson replied that is why he has the request out to the Contractor to what the  
Contractor would suggest we can do within the original budget. Mr. Donaldson stated the draft  
contract under review by the Town Attorney and Insurance Carrier and the contract will be ready  
should be Referendum pass.  
DISCUSSED  
RESULT:  
VII. OLD BUSINESS  
Discussion and possible action regarding furniture for the Gallup Hill School Building Project.  
1.  
Mr. Donaldson confirmed that the dollies for the pianos are there but cannot speak to the rest of  
the items. Mr. Donaldson provided the invoices, authorization and delivery confirmation  
receipts associated with the invoices. Chairman Gush requested that Mr. Donaldson take  
inventory for proof of receipt of the items listed. Mr. Tymniski questioned the response from  
Silver Petrucelli & Associates regarding these charges. Mr. Donaldson stated Silver did not have  
an explanation and forward the information. Mr. Tyminski stated Silver would have be the ones  
to order and sign off on delivery. Mr. Tyminski asked if the project was still open. Mr. Bonin  
informed the Committee that the project is currently in audit and is closed, there will be no  
reimbursement from the State for these charges. Mr. Tyminksi questioned where the money  
would come from to make a payment. Mr. Bonin stated the Town would need to cover these  
charges, there are some funds left in the project. Mr. Schneider requested the lien releases. Mr.  
Donaldson will request that information. This item will continue to the next meeting.  
NO ACTION  
RESULT:  
VIII. ADJOURNMENT  
Mr. Gush moved the meeting be adjourned, seconded by Mr. Hosey.  
The meeting adjourned at 6:13 p.m.  
VOTE: 4 -0 Approved and so declared  
Respectively Submitted,  
_______________________________  
Chairman Gush  
Permanent Municipal Building Commitee