Mr. Masalin noted more work needed to be done in preparing a proposal to establish a
separate Account to set aside some of the revenue generated from the Transfer Station
Fees and Recycling to be used for Transfer Station capital needs.
The Finance Committee agreed to remove this item from their agenda, and to revisit it
when Mr. Masalin was ready to present his proposal.
WITHDRAWN
RESULT:
MOTION to approve $45,000 in supplemental funding for the construction of the concrete floor
at the Town Green Pole Barn.
4.
Moved by Councilor Ingalls, seconded by Councilor Saums
Discussion: Public Works Director/Town Engineer Steve Masalin provided some
background stating at its December 8, 2021, meeting, the Town Council approved
$55,000 of American Rescue Plan Act (ARPA) funding for a concrete floor at the
Vo-Ag-Science Pole Barn at the Lower Town Green. He stated after securing quotes and
packaging the various facets (materials and labor) in the most cost-effective way possible
to reduce costs, coupled with as much in-house effort as possible, the total cost had been
estimated at just shy of $90,000, without contingency. He explained the Package
included labor supplied through the ezIQC program managed by the Gordian Group
through competitive CRCOG bidding. He stated the detailed scope of work, including
the citation of the Town portion, and cost of the Gordian Group portion ($61,433.07);
with the balance of the cost for materials and miscellaneous efforts supplied by the Town
amounts to about $27,500 was derived from direct quotes. He stated this approach was
proposed at the September 7, 2022, Finance Committee meeting and voted down, in an
effort to seek bids with the hope that the cost would come in lower.
Mr. Masalin went on to explain as a result of the Finance Committee’s September 7,
2022 meeting and with the consensus of the Mayor, the project went out to Bid (Bid .
#2023-04). The Bid results received on September 29, 2022 yielded responses from four
contractors noting that the bids ranged of $152,400 to $196,014. He stated if the previous
proposal of $95,000 was deemed to be excessive, the results of Bid #2023-04 were
clearly not acceptable.
Mr. Masalin continued to explain that he has since confirmed that the original Gordian
Group price of $61,433.07 remained good through the end of the year. However, he
stated because of the delay of seeking bids, the completion of the project was uncertain
within this timeframe, although any increase to this cost would not come close to
approaching the dollar amount that was received in response to Bid #2023-04. He stated
further deliberations with the Gordian Group and others would be required on a final
schedule.
Mr. Masalin went on to explain to accommodate any changes in materials costs he was
recommending, and he has requested this evening, increasing the Contingency by $5,000
to bring the total funding for the project to $100,000. He stated any amount that was not
needed would be returned to the unobligated balance of ARPA funding. He stated
although pouring a concreate slab seem to be a simple, straight forward project, that there