741 Colonel Ledyard Highway  
Ledyard, Connecticut 06339  
TOWN OF LEDYARD  
Permanent Municipal Building  
Committee  
Meeting Minutes - Draft Minutes  
Chairman  
Joseph Gush  
Special Meeting  
Monday, March 31, 2025  
5:30 PM  
Town Hall Annex - Hybrid Format  
REMOTE MEETING INFORMATION  
Join Zoom Meeting  
Meeting ID: 883 3938 2983 Passcode: 348228  
• +1 646 558 8656 US (New York)  
I.  
CALL TO ORDER  
Chairman Gush called the meeting to order at 5:30 p.m. at the Council Chambers, Town Hall  
Annex Building.  
II.  
ROLL CALL  
Committee Member Gary Schneider  
Committee Member Gerald Tyminski  
Chairman Joseph Gush  
Present  
Committee Member George Hosey  
Committee Member Elizabeth Peterson  
BOE Representative Jennifer Reguin  
BOE Representative Kate DiPalma-Herb  
Excused  
In addition, the following were present:  
Mathew Bonin - Finance Director  
Kristen Chapman - Mayoral Assistant, PMBC Staff Support  
Wayne Donaldson - Director of Facilities BOE  
Vincent Salinas - STV  
Scott Mitchell - Friar Architecture, Inc.  
III.  
RESIDENTS & PROPERTY OWNERS COMMENTS  
None  
IV.  
1.  
APPROVAL OF MINUTES  
MOTION to approve the PMBC Regular Meeting Minutes of March 3, 2025.  
APPROVED AND SO DECLARED  
Gerald Tyminski  
RESULT:  
MOVER:  
George Hosey  
SECONDER:  
5
1
1
Schneider Tyminski Gush Hosey Peterson  
AYE  
DiPalma-Herb  
Reguin  
EXCUSED  
NON-VOTING  
V.  
1.  
UPDATE ON JULIET LONG, GALES FERRY AND BOE CENTRAL OFFICE  
PROJECTS  
Progress Reports/Field Observations  
RECEIVED AND FILED  
RESULT:  
Update/Discussion on Roof Projects & Budget Documents  
2.  
Mr. Donaldson stated things at Juliet Long are moving along. The solar panel installation has  
begun at Juliet Long and the switch gear is due in April. There have no issued thus far with the  
solar panel installation. The roofing Contractor did come back and complete the punch list and  
is awaiting manufacturer verification, which may not take place until the walk pads are installed.  
The solar panels should be up and running before the end of the school year.  
Mr. Donaldson stated that Gales Ferry continues to move along. There was a leak in the gym  
that is currently being looked into. There is a dispute regarding the panel installation in the back  
of the building by the middle school was installed per the shop drawings or design drawings.  
Mr. Donaldson feels the Contractor would be obligated to fix that at no cost to the Town. Mr.  
Donaldson stated the Contractor has rescinded the change orders at the meeting on March 21st.  
A limited number of change orders have been submitted for review. Mr. Donaldson will present  
to the committee upon completion of the review.  
Mr. Donaldson stated the Central Office roof is complete and is awaiting punch lists. All of the  
metal work, low slope work is complete.  
DISCUSSED  
RESULT:  
MOTION to approve A Best Gutters, LLC Inv #22327 dated 3.10.2025 in the amount of  
$1795.00 for BOE Office Gutters.  
3.  
APPROVED AND SO DECLARED  
Gary Schneider  
RESULT:  
MOVER:  
Gerald Tyminski  
SECONDER:  
6
1
Schneider Tyminski Gush Hosey Peterson Reguin  
DiPalma-Herb  
AYE  
EXCUSED  
MOTION to approve Shipman & Goodwin LLP Inv #659790 dated 3.7.2025 in the amount of  
$472.00 for Contract Discussions - Remote Conference.  
4.  
APPROVED AND SO DECLARED  
RESULT:  
Gary Schneider  
Gerald Tyminski  
MOVER:  
SECONDER:  
6
1
Schneider Tyminski Gush Hosey Peterson Reguin  
DiPalma-Herb  
AYE  
EXCUSED  
**ADD ON**  
MOTION to approve The Imperial Company Restoration Contractor, Inc. Payment  
Application dated 12.31.2024 in the amount of $98,088.03 for Project 24-135 Gales Ferry  
School.  
5.  
Discussion:  
Mr. Donaldson stated this is the December Payment Application the Committee was advised  
not to pay previously as much of the roof panels still needed to be reattached. At this point  
most of that has been done and there is enough of a balance to cover the remaining areas that  
need to be redone as well as punch list items.  
APPROVED AND SO DECLARED  
Gary Schneider  
RESULT:  
MOVER:  
George Hosey  
SECONDER:  
6
1
Schneider Tyminski Gush Hosey Peterson Reguin  
DiPalma-Herb  
AYE  
EXCUSED  
VI.  
1.  
STV AND SILIVER PETRUCELLI UPDATE OF ROOF AND SOLAR PROJECTS  
MOTION to approve Silver Petrucelli & Associates Inv #25-123 dated 1.1.2025 in the amount  
of $4,250.00 for Project 22.331 Ledyard-Gales Ferry Roof and PV.  
APPROVED AND SO DECLARED  
Gary Schneider  
RESULT:  
MOVER:  
Gerald Tyminski  
SECONDER:  
6
1
Schneider Tyminski Gush Hosey Peterson Reguin  
DiPalma-Herb  
AYE  
EXCUSED  
MOTION to approve Silver Petrucelli & Associates Inv #25-279 dated 2.1.2025 in the amount  
of $4,250.00 for Project 22.331 Ledyard - Gales Ferry Roof and PV.  
2.  
APPROVED AND SO DECLARED  
Gary Schneider  
RESULT:  
MOVER:  
Gerald Tyminski  
SECONDER:  
6
1
Schneider Tyminski Gush Hosey Peterson Reguin  
DiPalma-Herb  
AYE  
EXCUSED  
MOTION to approve Silver Petrucelli & Associates Inv #25-1665 dated 3.1.2025 in the amount  
of $249.00 for Project 22.331 Ledyard - BOE Roof.  
3.  
Discussion:  
Mr. Donaldson stated this and item #4 on the agenda would be the last two payments to Silver  
Petrucelli & Associates for the BOE roof and Juliet Long roof. Mr. Salinas requested that Silver  
Petrucelli & Associates not bill the project in whole in order to keep the purchase order open for  
any additional costs that may be incurred. If the project is billed out in full that would close out  
the purchase order and if there is any additional billing, a new contract may be required.  
NO ACTION  
RESULT:  
MOTION to approve Silver Petrucelli & Associates Inv #25-1666 dated 3.1.2025 in the amount  
of $126.00 for Project 22.331 Ledyard - Juliet Long Roof & PV.  
4.  
5.  
NO ACTION  
RESULT:  
MOTION to approve Silver Petrucelli & Associates Inv #25-1667 dated 3.1.2025 in the amount  
of $850.00 for Project 22.331 Ledyard - Gales Ferry Roof and PV.  
APPROVED AND SO DECLARED  
Gary Schneider  
RESULT:  
MOVER:  
Gerald Tyminski  
SECONDER:  
6
1
Schneider Tyminski Gush Hosey Peterson Reguin  
DiPalma-Herb  
AYE  
EXCUSED  
VII. JULIET LONG HVAC PROJECT UPDATES  
JWL HVAC Project 2024 Updates  
DISCUSSED  
1.  
RESULT:  
Review and possible action on ReBid #LPS 24-9 State Project #072-001 HVACN - Ledyard  
Public Schools HVAC Replacement - Juliet W. Long School.  
2.  
Mr. Donaldson shared that three bids were received as a result of the rebid for the HVAC  
project. One bid was 3.1 million, another 3.2 million with the low bid at 2.67 million and that is  
the bid Mr. Donaldson recommends to the committee. Mr. Donaldson stated additional funds  
with be required based upon the bid amount as well as owner's representatieve, architect fees,  
commissioning fees, borrowing costs, and insurance. Chairman Gush added the total cost for the  
school projects was $8,550,000 which means $1,250,000 is needed placing the total project at  
$9,800,000.  
Chairman Gush stated the bottom line is money is needed over the initial appropriation and it  
has to go back to referendum. Chairman Gush added an owner's representative is also required  
by the ordinance, he has considered asking the Finance Committee and Town Council for a  
waiver but the cost is minimal compared to what is already being spent on the project. Chairman  
Gush stated that Friar Architecture has worked with all three bidders and there are no issues with  
any of the Contractors. Mr. Mitchell replied Friar Architecture has worked with all of the  
contractors and has had more experience with some but they are all qualified.  
Chairman Gush stated we need to push this forward to the Finance Committee and Town  
Council in time to add this to the referendum for the Town to vote on. If that happens there is  
still a chance of starting the project in June. Mr. Tyminski inquired about the timeline to get  
bonding if approved. Mr. Bonin stated there is bonding to deal with in August and this could be  
a part of that bonding.  
Mr. Shcneider inquired about the State Grant and the 62% reimbursement. Mr. Donaldson  
responded the State Grant will cover 62% of the original 2.25 million and the State will not  
increase that grant amount. Chairman Gush added the Town will be the paying this extra cost.  
Mr. Tyminiski stated it would be the 1.25 million plus the 30% paid by the Town for a total of  
around 2 million.  
Mr. Schneider stated the bid allowed for a certain amount of time to award the bid to  
Contractors, is it reasonable to notify the Contractor after the meeting tonight that the time  
frame may be a bit longer because we have to go to Referendum. Mr. Donaldson responded the  
Contractor is aware and requested a second motion to approve Nutmeg pending obtaining the  
additional financing. Mr. Tyminiski inquired if this would be a separate Referendum or with the  
budget. Chairman Gush responded yes it would be part of the budget Referendum.  
Ms. Chapman discussed the potential timeline for the request to move through the Finance  
Committee, Town Council and Referendum. Ms. Chapman clarified that this would be a  
separate question on the budget referendum.  
The Committee reviewed the original budget for the project compared to the total now needed to  
complete the project. The total project cost with the additional $1,250,000 required is  
$3,475,000.  
MOTION to recommend the Town Council appropriate an additional $1,250,000 (Increasing the  
appropriation and borrowing authorization to an aggregate $9,800,000) for Various School  
Improvement Projects, and authorizing the issuance of Bonds and Notes in the same amount to  
finance the appropriate.  
APPROVED AND SO DECLARED  
Gerald Tyminski  
RESULT:  
MOVER:  
Gary Schneider  
SECONDER:  
6
1
Schneider Tyminski Gush Hosey Peterson Reguin  
DiPalma-Herb  
AYE  
EXCUSED  
MOTION to approve Bid Proposal from The Nutmeg Companies Inc. in the amount of  
$2,673,520 for Bid # LPS-24-9 Ledyard Public Schools HVAC Replacement pending approval  
of an additional appropriation of $1,250,000 by the Town Council and through Referendum.  
Discussion:  
Mr. Donaldson requested the motion in order to have contracts reviewed by the insurance  
company and have everything in place so that if this passes we can immediately get contracts  
signed to move ahead this summer.  
APPROVED AND SO DECLARED  
George Hosey  
RESULT:  
MOVER:  
Gary Schneider  
SECONDER:  
6
Schneider Tyminski Gush Hosey Peterson Reguin  
AYE  
1
DiPalma-Herb  
EXCUSED  
VIII. OLD BUSINESS  
Discussion and possible action regarding furniture for the Gallup Hill School Building Project.  
1.  
Mr. Donaldson did receive the AIA invoices from the furniture manufacturing and is still  
waiting on the rest of the information requested by the Committee. Mr. Donaldson is waiting for  
proof of delivery and minutes. Mr. Bonin confirmed that these invoices were not paid.  
NO ACTION  
RESULT:  
IV.  
ADJOURNMENT  
Mr. Gush moved the meeting be adjourned, seconded by Mr. Hosey.  
The meeting adjourned at 5:30 p.m.  
VOTE: 5-0 Approved and so declared  
Respectively Submitted,  
_______________________________  
Chairman Gush  
Permanent Municipal Building Commitee  
DISCLAIMER: Although we try to be timely and accurate these are not official records of the  
Town.