Replacement and Photovoltaic Project.
Discussion:
Mr. Donaldson stated the Juliet Long roof is almost complete, with a few punch list items
remaining. Garland will not issue the Warranty until the Solar portion is complete.
APPROVED AND SO DECLARED
Kate DiPalma-Herb
RESULT:
MOVER:
Gary Schneider
SECONDER:
6
1
Schneider Tyminski Gush Hosey Reguin DiPalma-Herb
Peterson
AYE
ABSENT
Discussion and possible action on change orders for Gales Ferry School Roof Project.
The change orders will be reviewed at the March 20th Special Meeting.
4.
CONTINUE
RESULT:
VI.
1.
STV AND SILVER PETRUCELLI & ASSOCIATES UPDATE OF ROOF AND SOLAR
PROJECTS
MOTION to approve Silver Petrucelli & Associates Inv #25-123 dated 1.1.2025 in the amount
of $4,250.00 for Project 22.331 Ledyard-Gales Ferry Roof and PV.
This payment has been held at the request of STV to provide backup with dates for the
additional trips.
NO ACTION
VII. JULIET LONG HVAC PROJECT UPDATES
RESULT:
JWL HVAC Project 2024 Updates
1.
Chairman Gush reminded the Committee that the bid was refused at the last meeting as the sole
bidder was 1.5 million over budget. The RFQ was modified and the project has been re-bid.
Mr. Donaldson added the RFQ has gone out including value engineering as well as options for
the Contractor to use different types of equipment and also included more vendor options. The
bids are due back on March 17th and Mr. Donaldson will make a recommendation to the
Committee at the March 20th Special Meeting. Mr. Donaldson reiterated if there are less than
three bids, a bid waiver will be required through Finance and the Town Council. Mr. Schneider
inquired about the new timeline for the project. Mr. Donaldson added the completion time for
the project has been extended to December 2026. Mr. Donaldson added the Contractor will be
able to work during this summer and next summer as well as school breaks.
Ms. Dipalma-Herb stated the there was approval from the State for the Grant to be extended to
December 2026 and inquired what the full amount was approved during Referendum. Mr.
Donaldson replied 2.25 million, with the Grant at 1.37 (62%) of the total. Ms. Dipalma-Herb
inquired if that was a percentage of the completed project. Mr. Donaldson stated he asked if we
could up the project cost and the State replied that this is a fixed Grant, anything above the Grant
is the responsibility of the Town. Ms. Dipalma-Herb stated the Referendum approved the full
amount and is not sure why we would have to go back to referendum. Mr. Bonin replied there is