Project 212247 Ledyard Schools Juliet Long School.
APPROVED AND SO DECLARED
Gerald Tyminski
RESULT:
MOVER:
Kate DiPalma-Herb
SECONDER:
5
1
Schneider Tyminski Gush Hosey DiPalma-Herb
Reguin
AYE
ABSENT
MOTION to approve STV Inv# 90034679 dated 6.11.2025 in the amount of $31,916.75 for
Project 212247 Ledyard Schools Gales Ferry School.
3.
APPROVED AND SO DECLARED
Gerald Tyminski
RESULT:
MOVER:
Kate DiPalma-Herb
SECONDER:
5
1
Schneider Tyminski Gush Hosey DiPalma-Herb
Reguin
AYE
ABSENT
VII. JULIET LONG HVAC PROJECT UPDATES
JWL HVAC Project 2024 Updates
1.
Mr. Donaldson provided an update on the JWL HVAC project. Chairman Gush informed the
Committee that there is an issue with the cable run in the tunnel. Mr. Donaldson original design
was to run the piping in the ceiling to the custodial room and then run in the ceiling across to the
other side of the school to the other custodial room. It was determined that the piping could not
run through the ceiling due to steel beams preventing that path. Mr. Donaldson shared another
option was to run through the roof and across the roof which he as not keen on for a number of
reasons and suggested running through the tunnel. The electrician was happy to do that and
needed a design. The design came back significantly different than the original design. Mr.
Donaldson stated a new design and a quote should be available shortly. Mr. Donaldson will
come back to the committee with a change order. Chairman Gush stated all of the vent ducting
is in for the supply area. Mr. Donaldson shared all the ducting for the make up air is in and most
of the classroom units have been hung as well as the soffit work and sheet rock. Mr. Donaldson
stated there are three room with unique features, the kitchen, room 5A and the last LTA room.
The LTA (Ledyard Transition Academy) has three room in the school with their own entrance.
Mr. Donaldson invited the committee members to tour the building.
The committee discussed work that will still need to take place during school and after hours.
Mr. Schneider inquired if Mr. Donaldson was confident that the Building Official would issue a
temporary Certificate of Occupancy. Mr. Donaldson replied as long as all the fire ducts and
smoke ducts are sealed there should not be an issue.
JWL HVAC Owner’s Project Management Report - Colliers
2.
Mr. Warrington stated the contract was signed with Colliers on July 15 and they have begun
engaging in the field and attending meetings. took a look at the tunnel himself as it is a confined
space and wants to make sure everyone is safe. Mr. Warrington sated he looked at the
documents and the bid was to install in the ceiling and the steel ductwork only allows 16-18
inches above ceiling to the bottom of the roof deck and there are some steal beams that are pretty