Ledyard has continuously kicked the can down the road in addressing needed repairs
and improvements. He stated the town was spending $8,550,000 for these Board of
Education Various School Projects. Therefore, he stated that when they were
spending this much money it did not make sense to only do 9/10 of the project and
not include air conditioning/climate control in the Gym, Assembly Room and
Cafeteria to save a $110,000. He stated that he understands that these projects were a
lot of money; and that taxpayers do not like to have their taxes increase. However, he
stated that they have to look at the Big Picture.
Mayor Allyn addressed the timing of the HVAC Project at Juliet W. Long School. He
stated that the Projects would need to be completed by December, 2026 for the town to
be eligible to receive the Grant Reimbursement in the amount of 61.78% of the total
costs of the HVAC Project, noting that the State has already granted Ledyard an
extension to complete these Projects. He stated in an effort to meet the December, 2026
Project Completion Deadline that the Contractor has stated that they would need two
summers; which was the reason the Permanent Municipal Building Committee was
looking to include this request to increase the Bond Authorization on the May 20, 2025
Fiscal Year 2025/2026 Budget Referendum, so that they could begin work when school
lets out in June, 2025.
Chairman Rodriguez questioned if they present this supplemental authorization request
in the amount of $1,250,000 to the townspeople at the May 20, 2025 Annual Budget
Referendum, whether the Contractor has guaranteed that they would start the Juliet W.
Long School HVAC Project in June, 2025.
Mayor Allyn replied to Chairman Rodriguez stating that they do not have a guarantee
that the Contractor could even get the materials on-site by June, 2025. However, he
stated if the town does not complete the job by December, 2026 that they would not
be eligible for the Grant Reimbursement. Therefore, he stated that they were trying to
get some work done between June and August of this year (2025) ; and June and
August of the following year (2026). He stated although they do not have a guarantee,
that the Contractor indicated that they were going to do the work, and that they may
have at adjust their schedule to work during the School’s Christmas breaks, and other
school breaks, etc., and that they may possibly have to do some work on the roof
while the kids were in school, so they had things prepped and ready.
Chairman Rodriguez noted that the Contractor has talked about alternatives on how
they could complete the job. However, she stated in looking at the last two
Referendums for the Board of Education Various Projects that the First Referendum
in the amount of $8,367,500 was held on February 22, 2022; and the Second
Referendum to increase the amount by $1,825,000 for a revised total of $8,550,000
was held on October 17, 2023. She stated that she has never seen the town ask the
townspeople to vote on a Project during the May Annual Budget Referendum.
Mayor Allyn stated that the town has included financial questions on the Annual
Budget Referendum in past years. He stated that the Permanent Municipal Building
Committee (PMBC) would be forwarding their recommendation/request to the Town
Council to increase the current $8,550,000 Bond Authorization for the Board of
Education Roof Replacements & Various Projects by an additional $1,250,000; bringing