multifamily residential housing development & associated site improvements. (Submitted
2/24/25, Date of receipt 3/4/25, PH orig. scheduled 4/1/25, PH rescheduled to 4/22/25, PH
Cont. to 5/6/25, PH Cont. 5/27/25 with ext. granted, PH must close by 5/28/25, DRD 65 days
after close of PH)
Chairman DeBrodt read the letter from the applicant into the record marked as exhibit #36
requesting an extension of time to July 2nd. Director Burdick and Chairman DeBrodt
confirmed that the application would be continued to the IWWC Regular Meeting of July 1,
2025.
MOTION to continue the public hearing on application IWWC#25-5SITE to IWWC Regular
Meeting of July 1, 2025
CONTINUE
RESULT:
Dan Pealer
MOVER:
Michael E. Marelli
SECONDER:
4
2
DeBrodt, Pealer, Ribe, and Marelli
Thompson, and Graham
AYE:
NON-VOTING
IX.
NEW BUSINESS
IWWC#25-11SITE - 8, 9 & 11 Colby Drive, Ledyard, CT, (Parcel IDS: 68-520-8, 9 & 11) -
Applicant/Agent, Norm Eccleston for Owner, Habitat for Humanity of Eastern Connecticut
Inc. for regulated activities associated with construction of a multi-family residential
affordable housing development per C.G.S. §8-30g for 16 single-family and 11 duplex
dwellings & associated site improvements, inc. the extension of Colby Drive. (Submitted
5/27/25, Date of Receipt 6/3/25, DRD 8/6/2025)
A.
Chairman DeBrodt stated that the Commission would be accepting application
IWWC25-5SITE this evening. He asked if the applicant had a presentation this evening, and
they responded yes. Sarah Lufler, Executive Director of Habitat for Humanity, and Norm
Eccleston, members of Habitat for Humanity introduced themselves and their roles for the
organization. They displayed their Site Plan for the Commission.
Nancy Levesque, Civil Engineer of Benesch, introduced herself and her expertise. She spoke
about the wetlands on the property in relation to the preexisting infrastructure. She described
the function of the water flow and the detention basis. She spoke to the wetlands impacts as
well as the intended maintenance that is planned for the section of the property.
Commissioner Graham asked for clarification on extra water flow if the detention basin
should fill up. They discussed the water flow.
Director Burdick asked Ms. Levesque to point out both basins shown on the plan. Ms.
Levesque spoke about the drainage plans in relationship to the natural topography. Director
Burdick commented that Konover subdivision originally proposed multifamily buildings.
Hannah Gienau, Zoning Official, read her staff report into the record marked as file
document #10. She commented that the applicant has already been in discussion with the
department and there are several revisions to their site plan regarding the easement on the