· Emergency Services Building on Fairway Drive HVAC Systems failed (both
heating and air conditioning). Mr. Masalin stated the system was 21 years old and
he explained that they just completed heating system, which was paid for using
the Building Maintenance Reserve, in an unanticipated way.
· Parks and Recreation/Senior Citizens Facility on Van Tassel Drive HVAC
Systems failed (both heating and air conditioning). Mr. Masalin noted the air
conditioning system failed last summer and they had to use window units. He
stated the heating system was limping along, noting the 32 year old original gas
boiler was inefficient. It was also noted that this facility was used as a Cooling
Center during the summer months.
Mr. Masalin went on to state cost estimates were obtained thru the State Bid List to
complete the HVAC needs for both Emergency Services Building ($190,000) and the
Parks and Recreation/Senior Citizens Facility ($150,000). He stated the combined
estimated cost for the two buildings was $340,000. He stated although one of these
HVAC projects could be paid from the Building Maintenance Capital Reserve
Account, that it would completely exhaust The Building Maintenance Reserve
Account and he noted that other scheduled projects on the docket would have to be
set aside for lack of available funding. He stated he presently has not asked for more
of an appropriation this year for the Building Maintenance Reserve Fund than has
been made in the last few years. Therefore, he stated that they would need some
supplemental funding to address both the Emergency Services Building and the Parks
and Recreation/Senior Citizens Facility HVAC Systems, whether the funding comes
from a special appropriation or grant funding, which he did not see on the horizon.
Councilor Saums stated he was shocked by the estimated costs to replace the HVAC
Systems at these two town facilities. He stated although there was some residual
American Rescue Plan Act (ARPA) funding that they were planning to use the funds
for the Ledyard Center Sewer Extension Project. However, he stated because the
HVAC Systems were time sensitive that he would suggest using some ARPA funding
for the HVAC Systems, noting that the town would more likely be able to obtain
grant funding for the Ledyard Center Sewer Extension Project over HVAC Systems.
Mr. Masalin explained that the time sensitive part was because this State Bid
Contractor had exclusive commitments from May 1- September 1, 2023. He stated if
they do not move forward with these State Bid List proposals that they would need to
find another contract through a different proposal and hope that the function costs
would be similar.
Councilor Saums stated he had reservations about using the State Bid List Contractor
because the cost seemed high. Mr. Masalin noted in replacing the Town Hall HVAC
System last summer (2022) that they were able to bring the Contractor in under the
State Bid List noting that the cost was lower. Therefore, he stated if they were going
to use the competitive bid process that they would have a different means of
measurement of what their absolute dollar value would be based on that process. He
also noted that they would have to prepare the scope and specifications for the bid
process. Councilor Saums recognized the work and time involved to solicit
completive bids and he stated that based on the cost estimates already obtained that it