eligible for the Grant Funding. WPCA Chairman Ed Lynch stated the added value to
using Arcadis Engineering Consultants was that they document the work and have
worked with Connecticut’s Department of Public Health (DPH). Therefore, he stated
that Arcadis Engineering Consultants knows what reports the DPH would accept.
Councilor Buhle stated that once they know the cost for the Lead Survey Project that
it would be a WPCA expense, and therefore, it would impact the ratepayers and not
the taxpayers. WPCA Chairman Lynch stated that the WPCA does have some Capital
Funding, however, the capital account was designated to paint the Water Storage
Tanks and for Emergency Repairs. He stated when the Route 117 and Route 12
Water Projects were constructed that the projects were paid though Bonding, noting
although all the town’s residents did not benefit from those water projects that the
taxpayers approved for the town to bond the projects. Therefore, he stated that they
may have to go back to the townspeople for funding to facilitate the Lead Survey
Project. Mayor Allyn, III, noted that they were hopeful that they would receive the
Grant Funding.
Mr. Lynch stated that his question was: “What was Southeastern Connecticut Water
Authority (SCWA) was doing to meet the DPH’s requirement to conduct the Lead
Survey”. He stated the concern for Ledyard was that SCWA could tell the State
Department of Health (DEP) that they were done; and walk away. He explained per
state statute that the Ledyard WPCA would be required to take over the SCWA
Water System.
Mr. Lynch went on to state in 2018 Groton Utilities spent $54 million to rebuild their
80 year Water Plant,. He stated the Project was funded through Connecticut's
Drinking Water State Revolving Fund, which included a $15 million state grant and
$39 million in low-interest loans. He stated that Groton Utilities now had a very
advanced plant and their water was absolutely clean, noting that they have no
Per-and-Polyfluoroalkyl Substances, (PFA) in their water because they use turbidity
treatment. He stated part of the terms to receive the Department of Public Health
(DPH) Grant Funding was that Groton Utilities would interconnect all of the water
systems into SCWA. Therefore, Mr. Lynch stated that Ledyard was tied into the
SCWA System, explaining that this work was all done by Groton Utilities and it did
not cost Ledyard anything. He noted the cost just to put the interconnect to Norwich
cost $1.6 million, explaining that Groton Utilities and Norwich Public Utilities
connected their water systems via the Poquetanuck Cove Crossing Water
Interconnection which was completed in 2024. He stated this work involved the
installation of a 1,220-foot, metered water main to bridge a gap between the two
water systems at the Preston/Ledyard border to strengthen the resilience of both water
systems. He explained when SCWA lost a pump a few years ago all they had to do
was open the valve and they were able to keep water flowing for SCWA customers.
He explained that the water that went into the SCWA System was metered so the
WPCA could charge SCWA for the water they used. Therefore, he stated should
SCWA decide to walk away tomorrow that all the Ledyard WPCA had to do was
open the value, noting that no construction was required to do that. He stated if
SCWA was to go bankrupt that the Ledyard WPCA would have to run that water
system.