for the Central Office and the Juliet W. Long School. He explained the RFQ was a
two-part request: (Part A) Qualifications; and (Part B) Dollar Value. He stated the
dollar value part was kept in a sealed envelope that was held by Board of Education
Director of Facilities and Grounds Wayne Donaldson.
Mr. Schneider stated the PMBC interviewed both Firms noting that they were both
very qualified. He stated during the interviews the PMBC discussed with both Firms
what their process/procedure would be; and he noted the following:
STV Construction, Inc. - Mr. Schneider stated STV Construction, Inc., was willing
and included in their proposal having a full-time inspector on-site while the roof was
being installed, noting that the roof was the most valuable piece of the building
envelope.
Collier’s Project Leaders - Mr. Schneider stated Colliers Projects Leaders stated that
since they knew both of the roofing contractors, and because they knew that both of
the contractors were good, that their process would be to have a person drive/stop by
to see that they were starting the work right, and then leave, noting that Colliers
proposal included 2 - 4 hours of an inspector on each of the roof projects.
Mr. Schneider went on to state because they had issues with the roofs for the Schools
Consolidation/Improvement Projects (Middle School & Gallup Hill School) that the
PMBC was not comfortable with Colliers Project Leaders approach. He stated the
PMBC did ask Colliers what the cost would be to have a full-time inspector on the
roofs. However, he stated Colliers’s response was that a full-time inspector on the
roofs was not needed and that they would not recommend it, and it was left it at that.
Mr. Schneider stated based on the interviews and not knowing the bid proposal
prices, because they were in sealed envelopes, that the PMBC selected STV
Construction, Inc. He stated the proposals were as follows:
· Collier’s Project Leaders $63,301
· STV Construction, Inc. $141,470
Mr. Schneider stated because the PMBC thought $141,470 was high they authorized
Board of Education Director of Facilities and Grounds Wayne Donaldson to invite
STV Construction, Inc., back. He stated they had a good discussion, noting that the
PMBC told STV Construction, Inc., that they did not think they needed the added
expense of having their Project Manager on-site, and so they came back with a lower
price. He stated that the PMBC asked Mr. Donaldson to go back one more time to
STV Construction, Inc., to ask what their price would be to have an inspector on the
job full-time while the roofer was there, and having the Project Manger provide
oversight to make sure the paperwork was correct. He stated STV Construction, Inc.,
came back with the $91,496 proposal, which was higher than Colliers Project
Leaders’ proposal. However, he stated the STV Construction’s, Inc., proposal
included having the inspector on the job full-time.
Mr. Schneider went on to state that the PMBC was comfortable with how STV